Implementation

Six things have to be true before a MAS go-live.

New IBM Maximo Application Suite programmes led by engineers and consultants who have run asset operations themselves. The rungs below are what the schedule actually turns on, and each one states what it costs to hold a date against it while it is still false.

Electrical substation at dusk with cyan grid telemetry overlay across high-voltage gantries

The ladder

What has to be true, rung by rung

Read from the top. The lowest rung that is not yet true is where the programme will slip, whatever the plan says.

  1. Rung 6

    One cohort live and measured before the next

    Requires
    A first site or discipline in production, with a measurement of whether work is being recorded where the design says it should be, taken before the second cohort starts.
    Skip it and
    Every site inherits the same defect on the same day, and hypercare turns into a rescue with the same people covering nine locations.
  2. Rung 5

    A job that closes at the end of a shift

    Requires
    The mobile flow walked in poor signal, with gloves on, in the last ten minutes of a shift, by a crew rather than by a project team in a meeting room.
    Skip it and
    The job goes into a notebook and is typed up on Friday by somebody who was not there. The record is complete and nobody trusts it.
  3. Rung 4

    Interface counterparts pinned in writing

    Requires
    A named counterpart owner, a change window and either a test endpoint or an agreed stub for every interface, recorded before the plan is baselined.
    Skip it and
    The ERP team releases quarterly and the GIS team is mid migration. The go-live date assumed a change window nobody had asked for, and neither team reports to the programme.
  4. Rung 3

    Process decisions with an owner and a date

    Where the date is usually set
    Requires
    A decision register open from week one, and someone senior enough to overrule a site when two depots both defend their own practice.
    Skip it and
    Configuration is built ahead of the decision and rebuilt when it lands the other way. Configure both variants to avoid the argument and the estate carries two operating models, two sets of reports and one uncomfortable audit.
  5. Rung 2

    A hierarchy derived from how work is dispatched

    Requires
    A structure built from the level crews are sent to and the level the business reports at, then tested by placing twelve months of real work orders into it before anything is configured.
    Skip it and
    Crews book time to a parent covering half a site. Eighteen months later the question of which pumps fail most has no answer, and restructuring a hierarchy that already carries history and cost is a programme in its own right.
  6. Rung 1

    An asset register with one named owner

    Requires
    One person accountable for confirming that two records are the same physical item, and a profile of the register in numbers: rows, nulls, duplicates, orphans.
    Skip it and
    Everything migrates. On the first Monday a planner searches for a pump they have looked after for eleven years, gets four results, and goes back to the spreadsheet.

Scoping

What moves the cost and the duration

Five drivers, and the first outweighs the other four together.

Process decisions still open
Every open decision is design that cannot close and configuration that may be rebuilt. This is the largest single driver on almost every programme we price, and it is the reason the decision register is opened in week one.
Data readiness
How far the asset register, hierarchy, classification and work history sit from usable, and who is available to confirm that a duplicate is a duplicate. Scoped and funded under data migration into Maximo.
Integration count and counterpart availability
How many interfaces, and whether the ERP, finance and GIS teams can give you a test endpoint and a change window when the plan needs one. Designed and built under Maximo integrations.
Reach into the field
Sites, shift patterns, mobile users and languages. Training and adoption effort scale with people rather than with modules, which is the whole of a Maximo Mobile rollout.
Licensing shape
Which applications, and how the AppPoints are structured. A commercial decision that belongs early rather than at the end. See MAS AppPoints and licensing.

Run this before the date is set

Five statements, answered about your own estate

Work down them and stop at the first one that is not true today.

  1. 1

    One named person can confirm whether two asset records are the same physical item.

  2. 2

    Your asset hierarchy was derived from how crews are dispatched and how the business reports.

  3. 3

    Every process decision the design depends on has an owner and a date against it.

  4. 4

    Every interface has a counterpart owner who has given you a change window in writing.

  5. 5

    A crew has closed a job on the target mobile flow, in poor signal, at the end of a shift.

If you stopped early

The statement you stopped on is the rung the programme will slip against. Working on it now costs weeks; discovering it at UAT costs the date.

If every statement held

Configuration quality is then the thing that decides the outcome, which is the position every implementation is trying to reach and few reach by accident.

The shape of the engagement

What MaxIron commits to, and what it costs your side

Day one
A version-controlled baseline from MaxIron Blueprint

Tailored to your operation rather than a template you have to live inside.

Week one
The decision register opens

Every choice the design depends on, with a named owner and a date.

First go-live
One site or one discipline

Measured before the second cohort starts.

Ours outright
Design, build, integration, migration, test, cutover, support

A partner can be wholly accountable for all of it.

Credential
IBM Gold Partner through IBM Partner Plus, company 8294
Delivered in
United Kingdom, Ireland, United States, Europe

What this needed from the client

  • A person with the authority to overrule a site, available for roughly two hours a fortnight.
  • Supervisors released for training and testing, which comes out of operational hours.
  • Your own people to confirm that a duplicate record is a duplicate.
  • Change windows from the teams that own your ERP, finance and GIS systems.

Delivered

Two programmes, and what changed

  • UK building materials group

    Building materials

    Situation

    One division running SAP for maintenance, with asset management fragmented across business units.

    What changed

    Onto IBM Maximo in eight months from mobilisation to go-live, including a SQL Server to IBM DB2 conversion and integration with group ERP and finance.

    Read the case study →
  • UK industrial joint venture

    Industrial

    Situation

    A live Maximo environment inherited from an incumbent supplier, with no current record of what the platform was doing.

    What changed

    Service transition completed in two months, documentation captured, and the configuration issues that had accumulated where nobody was keeping track cleared.

    Read the case study →

Boundaries

Three responsibilities that stay inside your organisation

A proposal that implies otherwise fails in month five.

Process disagreements are settled by your authority

Where two sites disagree, we bring the options, the consequences and the evidence, then escalate. If escalation goes nowhere, design waits. That work belongs in business process optimisation before it belongs in a delivery backlog.

Data readiness is measured before the plan is signed

We measure it before design closes, and where the register is far off, that changes the plan and the price. An implementation on an unusable asset register delivers a system of record nobody trusts, on time and on budget.

Suite applications are scoped against the data that feeds them

Health, Monitor, Predict and Visual Inspection are separately licensed and carry real prerequisites: clean asset data, sensors, or failure history. Where those are absent we call the application premature and leave it out of the proposal.

IBM Maximo implementation, frequently asked questions

What decides whether a Maximo implementation succeeds?
Four things, in this order: whether the asset data is good enough to plan work from, whether the process decisions have named owners, whether the teams who own your other systems can give you a test endpoint and a change window, and whether a crew can close a job at the end of a shift without a workaround. Configuration quality matters, and it is rarely what decides the outcome.
How long does a MAS implementation take, and what drives the cost?
Duration and cost follow the five drivers above, with open process decisions outweighing the rest. Module count is a poor predictor of either. Our Maximo implementation timeline guide sets out how the phases sequence.
Who owns data readiness, us or you?
The work can be ours, the ownership stays yours. We profile the register, quantify the gap, migrate samples and do the heavy lifting on cleansing and load, using MaxIron Data Loader where volume justifies it. Confirming that a duplicate is a duplicate, or that an asset is out of service, is a call for your people.
What if our sites cannot agree on a single process?
That is the finding, and we escalate it rather than configure both variants. We bring the options, the operational consequence of each, and evidence from your own work history. Somebody in your organisation with the authority to overrule a site makes the call, and it is recorded with their name and the date.
Do you start from a blank configuration?
No. MaxIron Blueprint installs a pre-configured, version-controlled baseline on day one, so early design effort goes to what is genuinely specific to your operation rather than to rebuilding standard capability.
Which MAS applications do you implement, and do you work outside the UK?
Manage and mobile patterns on every programme, then Monitor, Health, Predict and Visual Inspection where the data that feeds them exists. MaxIron delivers in the United Kingdom, Ireland, the United States and Europe as an IBM Maximo partner, IBM Gold Partner through IBM Partner Plus as company 8294.

Bring the process your two sites disagree about.

One real disagreement and one real data extract. We will show how the decision gets framed, who has to own it, and what it changes in the design. That predicts your implementation better than a module walkthrough.

Bring this to the first call

  • An export of your asset register, however untidy, and roughly how many records you think are duplicates
  • A month of real work orders, including the ones that were closed badly
  • The one process your sites do differently and both defend
  • The three reports your executive team asks for every month
  • The name of the person who can overrule a site, and whether they are available for two hours a fortnight